Pavement Rehabilitation Project starts Oct. 6

PEORIA -- Weather permitting, work to repair a section of Mt. Hawley's runway and taxiway is slated to begin Friday, Oct. 6, and the runway is scheduled to be closed Oct. 16-20.

Hangar tenants at Mt. Hawley will have limited to no access to their aircraft during construction, particularly during the day.

Pilots needing to fly during the anticipated runway closure may contact Airport Director Gene Olson or Operations Director Doug Palmer at (309) 697-8272, ext. 100, and arrangements to briefly relocate aircraft to the Peoria International Airport can be made.

"We apologize for any inconvenience this work may cause, and I appreciate everyone's cooperation as we work to improve the Mt. Hawley Airport," Operations Director Doug Palmer said of the two-phase project, which is made possible by a Federal Aviation Administration grant.

Hangar tenants will be notified directly with instructions and a construction timelime. That tentative construction schedule is also listed below.

As a safety precaution, pilots are asked to tow all aircraft to an area outside construction prior to starting the engine. Anyone needing assistance in moving their aircraft, please contact 3MY Line Service at (309) 303-1003. After hours, please contact PIA Airport Operations at (309) 697-8272, ext. 110. 

 

Tentative Construction Schedule

Phase 1 (Western-most row of hangars and south connecting taxiway)

Friday, Oct. 6: Milling and priming begins. No aircraft access during the day. Emergency aircraft access after business hours. Aircraft must be towed from construction area prior to starting engine.

Saturday, Oct. 7: Primer curing. Aircraft must be towed from construction area prior to starting engine.

Sunday, Oct. 8: Primer curing. Aircraft must be towed from construction area prior to starting engine.

Monday, Oct. 9- Wednesday, Oct. 11: Paving operations. No aircraft access during the day. 

Phase 2a (Portable hangars and centerfield connecting taxiway)

Thursday, Oct. 12: Milling operations. No aircraft access during the day. Emergency aircraft access after business hours.

Friday, Oct. 13: Priming operations. No aircraft access during the day. Emergency access after business hours.

Saturday, Oct. 14: Primer curing. Aircraft must be towed from construction area prior to starting engine.

Sunday, Oct. 15: No work scheduled. Limited aircraft access. Aircraft must be towed from construction area prior to starting engine.

Phase 2b (Runway repair and phase 2a paving)

Monday, Oct. 16 -- Friday, Oct. 20: Runway 18/36 is closed for paving and striping.

 

                                                ###

 

 

 

 